Buffalo Speedway at Highway 59 reopens ahead of schedule

No description found

HOUSTON – The Buffalo Speedway project wrapped up Monday.  The road is is back open and ahead of schedule.

The exits were closed in both directions at Highway 59 to smooth out the street in the area.  The project, which began on Oct. 22, was expected to take 30 days, but was completed ahead of schedule.

Recommended Videos



The Southwest Freeway north and southbound frontage roads at Buffalo Speedway did remain open for commuters.

However, only one through-lane was available at the intersection while the left lane was used for U-turns only and the right lane was used for turning right onto Buffalo Speedway.

TxDot was to pay the contractor up to $70,000 if they finished a majority of the project before Nov. 21, but if the work continued beyond that, date the contractor faced a penalty of $10,000 a day. 